A proposed $40-million biogas plant could produce as much as 200,000 gigajoules of renewable natural gas annually with “minimal” greenhouse gas emissions, according to an environmental impact assessment prepared for developers.
That would amount to 13.3 per cent of the province’s 1.5 million gigajoules of natural gas produced last year, according to Statistics Canada.
The project proposed by Bio Voltex Ltd. near the Headwater natural gas terminal in Penobsquis is currently in the provincial environmental review stage. The 117-page assessment document prepared by consultants Stantec was filed in March, and contains information about the project and its projected impacts on the air, landscape and socioeconomic environment.
As part of the plan, farmers deliver agricultural waste, including livestock manure, vegetable, potato and fish waste, to the plant, which uses a process called anaerobic digestion to separate it into renewable natural gas and a byproduct called digestate that can be returned to farmers for use as fertilizer.
The proponents say that benefits include “diverting organic waste from landfills, reducing overall greenhouse gas emissions and potential adverse effects to land and water,” as well as reducing dependence on fossil fuels and diversifying the province’s energy sources. The project is “largely privately funded,” although Bio Voltex may seek grant funding, the review said.
The site is on 4.7 hectares of a 80 ha plot of land in Cardwell Parish, with no applicable zoning or planning documents, with the nearest residence about 350 metres away. The land, leased to the proponents for 20 years with an option to extend, is currently vacant and had been used for agriculture dating back to the 1950s, according to the review.
Developers chose the site because of its proximity to the natural gas pipeline, feedstock sources and transportation infrastructure according to the review, and with other possible sites lacking in suitable zoning, infrastructure and located far from feedstock producers.
Feedstock material would arrive by truck in the operations building and be loaded into a depacking unit by a skid steer or forklift or manually depacked, with the waste discharged into a reception pit. The building would be closed for odor management and noise management, with air filtered through activated carbon filters, the review said, with the filtered air containing “low odor (ammonia and hydrogen sulphide) that is predicted to not be detectable.”
The reception pit, which would be a closed-top concrete structure approximately 400 cubic metres, would direct the manure and organic waste into an anaerobic digester, which would consist of one or two 13,000 cubic metre tanks with paddle mixers that operate on 50-day retention cycles, according to the review. The resulting biogas would be sent to a treatment and upgrading system to reduce moisture, remove hydrogen sulphide, carbon monoxide and “volatile organic compounds,” the review reads, creating natural gas with 96.5 per cent methane purity and compress it to be sent by pipeline to the terminal.
The digestate byproduct would go to a separate tank, with liquid digestate flowing to a closed lagoon and solid digestate separated for “agricultural re-use,” according to the review. The plant would take about a year to build, with commissioning in the second half of 2027, and employ approximately 50 to 90 workers during construction and three full-time employees when finished, the review said.
The closed-loop anaerobic digestion system limits air containment “under normal operating conditions,” the review said, with a safety flare set off to burn excess biogas if necessary. The biogas process was said to limit the uncontrolled methane release that would come from manure regularly, consultants say in the review.
Emissions from biological sources, such as CO2 removed from the biogas and vented to the atmosphere, are accounted for separately from fossil fuel emissions, which are an “addition” to the carbon cycle, the review said. Construction and the operation of the natural gas boiler will generate emissions, the report said, with the project using 9,600 gigajoules of natural gas and 12.7 gigawatt-hours annually.
The emissions would amount to the equivalent of 11.3 kilotonnes of carbon dioxide per year, or 4.7 kilotonnes if you remove the biological-source emissions, the report said. That’s “a small fraction of New Brunswick’s annual GHG emissions,” which amounted to 12,500 kilotonnes in 2022, and would not be enough to trigger provincial and federal emissions reporting, the consultants say.
The renewable natural gas produced by the project features a 99 per cent decrease in emissions intensity compared to fossil fuel natural gas, due to the accounting for biological-source emissions, according to the review. That means if the plant produced 180,000 gigajoules a year of renewable natural gas, the emissions savings would amount to the equivalent of nine kilotonnes of carbon dioxide per year compared to fossil fuel natural gas, the report said.
The plant would be projected to convert 115,000 to 135,000 tonnes of organic waste into 200,000 gigajoules of natural gas annually, according to consultants. That’s an assumption based on 8,760 annual operating hours, the review reads.
According to Statistics Canada data, that would amount to 13.3 per cent of the 1.5 million gigajoules of “marketable production” of natural gas produced last year in New Brunswick. The province delivered 19.3 million gigajoules of natural gas to consumers in 2025, including residential, commercial and industrial consumption, most of which came from imports, the data read.
The emissions from the project are not likely to exceed ambient air quality criteria, including for odor, the review said, and the plant will monitor flowrate and CO2 content of offgas, volume of gas combusted in the boiler and any gas sent to the flare. Filtered exhaust air will have odors of rotten egg (from hydrogen sulphide) or urine (from ammonia), but the consultants say it will mix with ambient air and is “not expected to be detectable at the nearest residence.”
The project site is a “historically disturbed site” with past agriculture use, but the clearing will result in the loss of a “small, unregulated wetland” not large enough for a provincial Watercourse and Wetlands Alteration permit, the consultants said. Clearing will be planned outside of the breeding bird season to “limit potential effects,” according to the review.
Outreach has included information distributed to 16 Indigenous nations who were also offered investment opportunities, the review read. Notices were distributed to Canada Packers Road, along Hwy 114 between CPR and Royal Gardens Road, Penobsquis Road, Church Road, and posted at the Three Bears campsite, and an open house is planned, according to the review.
Erosion and sediment control measures will be in place, and will be designed for “high levels of precipitation,” the review. Operators will implement regular maintenance to guard against failure of the odor control system as well as fire protection systems, according to the review.
Bio Voltex CEO Scott Walton told Brunswick News last month that there’s been “lots of progress” on the project, and that they are on track to start construction this year. In an email June 16, he said the review process, including receiving and responding to comments from panelists, has been “very positive” thus far.
“We’re submitting our second response this week,” Walton said Tuesday. “The second round (of comments) was great, it was again more clarifying questions and procedural questions.”
Walton said they’ve been making plans around detailed engineering and design and have got financing in place. He said they have a baseline of suppliers lined up to provide feedstock, but said they’re open to speak anyone with more than 1,000 tonnes of organic material, noting that they will charge “low to no” tipping fees compared to other options.
By Andrew Bates, Local Journalism Initiative Reporter
Original Published on Jul 06, 2026 at 08:35
Recent Comments