New Westminster’s parks and recreation plan includes extending Pier Park further east past the area that was destroyed by a fire in September, 2020.MARIO BARTEL/FRESHET NEWS

A new downtown community centre, a covered multi-sport box, a disc-golf course and an indoor ice sheet are among the parks and recreation amenities proposed in New West’s new parks plan.

New Westminster city council recently approved the People, Parks and Play parks and recreation comprehensive plan. It includes a 10-year implementation strategy and a long-term vision extending to 2050.

Dean Gibson, director of parks and recreation, said the plan identifies ways to “catch up” to the meet today’s needs and to “keep up” with the city’s needs as its population grows.

Corrinne Garrett, deputy director of recreation services and facilities, said New Westminster has evolved as a dense, urban centre since the last parks plan was completed in 2008.

“As a result of provincial housing mandates, there is imminent need for bold, creative solutions to keep pace with population growth and eliminate barriers to access in order to ensure a livable, connected community,” she said.

Erika Mashig, deputy director of parks, policy and planning, said New Westminster’s parkland supply has not kept pace with population growth. She said the city has seen a 50 per cent decline in its park land supply ratio — dropping from two hectares of active parkland per 1,000 residents to one hectare per 1,000.

“Without intervention, this could continue to fall to 0.79 hectares, with a projected population growth to 2034,” she said.

Because it’s “essential” that residents have a park close to home, Mashig said the city will work to ensure every resident lives within 330 metres or a five-minute walk to an active park. She said the data shows the city’s downtown and the west side will be in greatest deficit and will be prioritized for new parkland.

“The city currently has one hectare per 1,000 population of active park land citywide,” she said. “Based on high-growth population projections, with this we will need to add 12.3 hectares of parkland to maintain that ratio in the future.”

People, Parks and Play also addresses the need for additional indoor recreation facilities.

“As the population grows, and growth projections target density areas around transit, future indoor facilities will be required to keep up to growth projections,” Garrett said.

Based on 2034 population projections, Garrett said a 2,800-square-metre community facility and a third ice sheet will be required to meet community needs.

According to a staff report, implementation of the plan will be supported by a 10-year, $134.5-million financial strategy.

Capital projects included in the plan include:

· Converting the existing grass field at the Ryall Park to artificial turf

· Upgrading the Hume Park lacrosse box to a multi-covered sport facility

· Replacing Queen’s Park Stadium and the bandshell

· Completing the western expansion of Westminster Pier Park and working toward the redevelopment of the Pier Park fire site

Mashig said the plan identifies a list of capital projects to be triggered by population thresholds.

“These amenities and facilities are excluded from the 10-year implementation plan to maintain the flexibility to scale delivery based on actual pace of development and population growth,” she said. “So, this ensures we are building exactly what the community needs, when they need it.”

According to staff, the 10-year implementation plan is estimated at $127.2 million, of which about $63.6 million is already identified in the city’s five-year financial plan.

Mayor Patrick Johnstone supported approval of the plan but proposed an amendment to have staff begin feasibility work and develop a community consultation plan on the following projects that are identified as high priority in the plan:

· Upgrading the multi-sport courts and conversion of at least one to a covered multi-sport facility

· Constructing a new multi-purpose community and recreation space in or immediately adjacent to the downtown neighbourhood

· Upgrading the playing surface and amenities at Westburnco Park to better utilize this large recreation space

· Adding a new full-size ice sheet

Staff will report back to council on timelines and resource requirements to begin moving these projects forward in an expedited fashion.

“We need to start this work now and show the intent that we are going to get this work done and start the important work of putting the pieces in place for the next phase of developments,” Johnstone said. “These projects take some time, feasibility studies to understand the costs and challenges, and public consultation to determine the details of what we deliver. And that work needs to start now.”

Coun. Nadine Nakagawa said she’d like staff to report back on the progress of implementing People, Parks and Play.

“The community deeply cares about this parks and rec plan. They are really excited to see everything that’s in it,” she said. “It’s a big plan. It’s an audacious plan.”

By Theresa McManus, Local Journalism Initiative Reporter

Original Published on Apr 29, 2026 at 18:00

This item reprinted with permission from   Freshet News   Burnaby, British Columbia

Comments are Welcome - Leave a reply below - Posts are moderated