Beachburg — Improvements to the Beachburg water treatment plant – and the associated costs – continue to be a work in progress.
The most recent retrofit of the plant, which was built in 1955, was completed in 1994. The current renewal and optimization project addresses vital components of the plant that are reaching the end of their useful life. The improvements include new digital controls and monitoring devices in order to reduce energy consumption and carbon emissions, and to increase capacity and avoid redundancy.
The construction tender amount was $1,568,000. However, as the work progresses, other deficient areas are being discovered. To date, change orders to address new-found problems have added $117,433 to the project cost which, along with engineering costs and HST, have added up to $2,075,648.
At its March 18 regular meeting, Whitewater Region (WWR) council approved three more changes to the specifications for the project, adding another $59,427 to the cost.
In her report to council, Environmental Services Superintendent Deanna Nicholson explained the plant’s interior plumbing is connected to the high-lift header of the plant and is composed of a combination of galvanized and copper fittings and pipe.
“This connection is showing signs of severe corrosion and is nearing the end of its useful service life,” she said. “Additionally, the reduced-pressure backflow preventors do not meet the requirements of the current Ontario Building Code.”
Further, there is a looming potential issue with a valve in the system.
“The isolation valve on the connection was tested and currently operates, but it has limited life remaining, and it is recommended to replace this portion of the pipe with a new isolation valve, a reduced-pressure valve, and a backflow preventor to restore the useful service life of this integral part of the building’s plumbing,” she said. “Although this work can be postponed, if it starts to leak, it could become an emergency repair, resulting in higher costs to the township. Therefore, it is recommended to issue a change order for this work while the construction trades are completing the work at the plant.”
Isolation valves on four high-lift pumps that have already been replaced have also raised red flags.
“A similar situation, these were valves that were being looked at while other work is going on,” Ms. Nicholson said. “During the time that the high-lift pumps were being replaced those isolation valves were used, and again they became obvious during that work that the valves were not operating as they should. One was leaking for them while they were trying to complete the work.
“So again, these valves are reaching the end of their useful life. The same situation where these are critical valves for this plant. They don’t need them at this exact second — they were able to complete the work that they needed to do as part of the bigger project. But if it were to come up again in the future where they needed to rely on these valves, they wouldn’t necessarily do what they need to do. So again, the consultant has recommended we issue a change order while the trades are on site and able to complete them.”
The third item recommendation is for a second post-filtration chlorine analyzer that would be installed at the end of the filtration process.
“This would detect a low chlorine issue early, so the plant would shut down immediately and the problem could be corrected without continuing to push unchlorinated water into the clear valves which is like the holding tanks beyond,” she noted. “Currently, there is a chlorine analyzer at the exit of the plant so at the exit of the clear valves as it’s entering the distribution system and we will get an alarm if we have a low chlorine situation. Unfortunately, where it is, it doesn’t allow them to actually correct it. Installation of an additional analyzer earlier in the process would allow us to catch a problem and fix it before it becomes an issue.”
Ms. Nicholson said the three additional contemplated change orders, if approved, would bring the total project cost, including non-refundable HST, to $2,136,121. Grants are expected to fund approximately 73 percent of that cost, leaving the municipality to pick up the remaining 27 percent, which totals just over $550,000.
Councillor Mike Moore said he was in favour of these changes even though some of it is over budget.
“If we leave this, we run the risk of having to pay extra money for an emergency call, and the chance of not having the material on hand at the time to keep things running,” he remarked. “I would like to be proactive and proceed with this in as timely a fashion as possible, provided the treasurer can find the cash.”
Mayor Neil Nicholson noted the treasurer has already identified the source of the funds payable by the township.
“They will be coming out of reserves,” he said.
Councillor Chris Olmstead said, according to his calculations, the $2.062 million project will end up being $37,000 over budget if the change orders are approved.
Director of Public Works Lane Cleroux noted that spending the extra money will result in more improvement to the water plant.
Councillor Joe Trimm, while conceding he is “no expert,” said the pictures provided as part of the report showed the components, in their present state, are “a disaster waiting to happen.”
“I agree with Coun. Moore that it’s good to get on this as quickly as possible because if there is, God forbid, another break, that adds to this cost,” he said. “And so, hopefully, we can get through this spring without a break.”
Ms. Nicholson told council the project is getting very close to completion.
“We have most of the equipment on site now,” she said. “They’re waiting on a few filters to be installed, and so we’re hoping we have a couple of months left and then this will all be done.”
The motion to approve the three change orders passed unanimously.
By Marie Zettler, Local Journalism Initiative Reporter